By Matthew Renda

The California State Auditor rebuked the agency in charge of implementing the state’s high-speed rail project Thursday, finding lack of planning and poor oversight has led to cost overruns plaguing the Golden State’s efforts.

“Despite being aware of risks associated with beginning construction before completing critical planning tasks, the authority began construction in 2013 – a decision that has led to contract changes, project delays, and cost overruns,” the state auditor said in a report released Thursday.

The audit prompted another round of criticism and questions about the project’s viability from state lawmakers.

“The nonpartisan state auditor has confirmed in the release of today’s audit what we have known about this disastrous rail project: flawed internal oversight that has resulted in wasted hard-earned tax dollars,” said Assemblyman Vince Fong, a Republican from Bakersfield and a frequent critic of the infrastructure project. “Billions of dollars are being poured into a project that does not resemble anything that was told to voters a decade ago.”

When California voters first passed Proposition 1A greenlighting the project in 1996, the initial price tag was pegged at about $33 billion with a completion date of 2018. The cost estimate has since climbed to $77 billion and plans now call for trains to start running in 2022.

The auditor blasted “flawed decision making and poor contract management” for the cost overruns and delays. The report also notes the California High-Speed Rail Authority must work twice as fast to bring the project to completion in the next four years or it risks losing $3.5 billion in federal grants.

The authority said it has addressed many of the shortcomings highlighted by the state auditor and plans to implement the agency’s key recommendations.

“Many of the recommendations are similar to steps we have previously identified through our own internal reviews,” said authority board member Mike Rossi. “The authority will promptly implement all of the auditor’s recommendations, as we did following the last audit that was conducted in 2012.”

The auditor took particular issue with cost oversight at the authority, saying that while 56 people were tasked with oversight of more than $5 billion in contracts, high turnover in a department that had only three full-time managers hampered the efforts. This in turn created significant problems as the authority must manage a range of different construction companies, contractors and subcontractors who are carrying out various pieces of the nation’s largest infrastructure project.

Finally, the authority has outsourced much of its contract oversight to outside consultants, but the state auditor warned such consultants may or may not have the best interests of the state and its taxpayers at heart.

The auditor said the authority must “Improve its contract management by hiring and assigning full-time and experienced contract managers who are state employees, monitoring contract managers compliance with policies and holding contract managers accountable for their performance.”

The authority has said many of the cost overruns came from difficulties in securing rights-of-way through the Central Valley, where construction is currently underway.

Rossi noted Thursday that the authority has taken recent steps to move the project forward more rapidly and efficiently under the guidance of the newly appointed CEO Brian Kelly, who came on board this past February.

The high-speed rail was championed by outgoing Governor Jerry Brown, though it remains unclear if his successor will be as enthusiastic a supporter. Governor-elect Gavin Newsom mostly dodged questions about the viability of the project on the campaign trail.

Comment On This Story
COMMENT POLICY: We welcome comments from individuals and businesses. All comments are moderated. Comments are subject to rejection if they are vulgar, combative, or in poor taste.
REAL NAMES ONLY: All posters must use their real individual or business name. This applies equally to Twitter account holders who use a nickname.

4 Comments

  1. Dave Rickmers says:

    China builds railroads really well (we taught them) and fast. I hope we spent a billion on automated track laying equipment.

  2. So Cal Guy says:

    A continued waste of tax payer money. I would really like to see Newsome’s first real big decision for California be to ditch this $77 Billion Dollar Disaster, pay back the grant money and reallocate the money to projects that are needed for California…not wanted. Brown needs to go and take his train with him. I know it’s wishful thinking…

  3. Patricia Probasco says:

    I just read that Gov. Brown did not approve a bill that would have helped clear the dead wood in our forest, giving the money to his train. Because of them unable to manage the forest, we just had the most deadly fires in California. Hope you sleep well mr. brown.

  4. Vicky Hanneman says:

    What a fiasco!! We all need to get Katie Hill involved in fighting this and get the Federal Government to stop funding Jerry Brown’s “full employment act” for his cronies!!

Leave a Comment


SCV NewsBreak
LOCAL NEWS HEADLINES
Friday, May 24, 2019
SCV Detectives Issue Sketch of Indecent Exposure Suspect
Santa Clarita Valley Sheriff's Station detectives released a composite sketch Friday afternoon of the man suspected of indecent exposure in Towsley Canyon Park on Thursday, May 16.
Friday, May 24, 2019
SCV Deputies Rescue Suicidal Man on Canyon Country Bridge
Santa Clarita Valley Sheriff’s Station deputies rescued a suicidal man from a Canyon Country bridge on Thursday night, station officials reported.
Friday, May 24, 2019
Cannabis Tax Revenue in First Quarter 2019 Nearly Doubles 1Q 2018
The California Department of Tax and Fee Administration reported tax revenue numbers Friday totaling $116.6 million for cannabis sales for the first quarter of 2019, nearly doubling revenue over the first quarter of 2018.
Keep Up With Our Facebook

Latest Additions to SCVNews.com
1971 - Community preview night (pre-grand opening), Magic Mountain [story]
1956 - Placerita Canyon State Park dedicated [story]
Oak of the Golden Dream
1966 - Mustang Drive-In theater opens on Soledad Canyon Road [story]
Mustang Drive-In
The Beer Institute and the National Beer Wholesalers Association have released their "Beer Serves America" economic report on the nation’s beer industry, showing the U.S. beer industry supports more than 2.1 million jobs and contributes more than $328 billion to the U.S. economy.
Report: Beer Industry Creates 2 Million Jobs, Pours $328B into U.S. Economy
Los Angeles County's Department of Animal Care and Control has received a 2019 Achievement Award from the National Association of Counties for DACC's "Pawsitive Steps" program.
LA County Animal Care Wins National Achievement Award
Santa Clarita Valley Sheriff's Station detectives released a composite sketch Friday afternoon of the man suspected of indecent exposure in Towsley Canyon Park on Thursday, May 16.
SCV Detectives Issue Sketch of Indecent Exposure Suspect
Santa Clarita Valley Sheriff’s Station deputies rescued a suicidal man from a Canyon Country bridge on Thursday night, station officials reported.
SCV Deputies Rescue Suicidal Man on Canyon Country Bridge
The Valley Industry Association will host "Cocktails and Conversation: An Evening with Kathryn Barger" at the Valencia Country Club on Wednesday, June 26, from 6 p.m. to 8 p.m.
June 26: VIA to Host Evening with LA County Supervisor Kathryn Barger
The Santa Clarita City Council will hold its next regular meeting Tuesday, May 28, starting at 6 p.m. and preceded by a special meeting at 5:30 p.m. for labor negotiations.
May 28: Santa Clarita City Council Special, Regular Meetings
The California Department of Tax and Fee Administration reported tax revenue numbers Friday totaling $116.6 million for cannabis sales for the first quarter of 2019, nearly doubling revenue over the first quarter of 2018.
Cannabis Tax Revenue in First Quarter 2019 Nearly Doubles 1Q 2018
To improve Memorial Weekend holiday traffic flow on Interstate 5 through the Santa Clarita Valley, the California Department of Transportation opened a fourth northbound lane Wednesday where only three lanes were open in recent months due to construction.
Caltrans Opens New I-5 Lane in Time for Memorial Weekend
U.S. Rep. Katie Hill, D-Agua Dulce, will celebrate Memorial Day in all three valleys of California's 25th Congressional District with events on both Saturday, May 25 and Monday, May 27.
Hill to Spend Memorial Weekend in 3 Valleys
After getting rained out on Wednesday, the JetHawks and Inland Empire 66ers split a doubleheader Thursday night at San Manuel Stadium.
JetHawks Split Thursday Double-Header with 66ers
The Los Angeles County Health Officer has called a Cold Weather Alert due to the National Weather Service’s forecast for low temperatures for the Los Angeles County mountain areas on Sunday, May 26.
Cold Weather Alert Called for Local Mountains on Sunday
The Santa Clarita City Council invites the public to attend an unveiling ceremony in front of the Valencia Library for the newest public art sculpture in Santa Clarita called “Imag_ne” by Australian artist Emma Anna on Wednesday, June 5, at 10 a.m.
June 5: Unveiling of ‘Imag_ne’ Public Art Piece at Valencia Library
While college is a faraway thought for most junior high students, Mark Gray was not only thinking about college, but also saving up for it, too.
Hard Work Pays Off for COC Graduating Student
Detectives from the Santa Clarita Valley Sheriff's Station seek the public's help to identify a man suspected of stealing personal items from a locker at the LA Fitness club in Centre Pointe.
SCV Detectives Seek ID of Suspected Gym Locker Thief
A housing development plan for Canyon Country, introduced in 2006 when the housing industry entered the Great Recession, was dusted off this week and given a one-year extension by regional planners.
Regional Planners OK Time Extension for Canyon Country Development
Governor Gavin Newsom on Friday issued a proclamation Friday officially declaring Monday, May 27, 2019, as “Memorial Day” in the state of California.
Newsom Issues Proclamation Declaring Memorial Day
While still currently under construction, the development project formerly known as Newhall Ranch, which is also part of Valencia, will bring kids into the Saugus, Castaic and Newhall elementary school districts, as well as the William S. Hart Union High School District, local school officials have been told.
FivePoint Development to Add Enrollments to 4 SCV School Districts
A Santa Clarita woman who led police on a pursuit from Valencia to Tarzana while driving an RV with two dogs inside on Tuesday was charged Thursday with nine felony counts, according to the Los Angeles County District Attorney’s Office.
Woman Driving RV in Police Pursuit Charged with 9 Felonies
1860 - Colonel Thomas F. Mitchell arrives in Soledad Canyon [story]
T.F. Mitchell
After one and a half hours inside a crumpled car, the last of two people trapped was freed from the wreckage.
3 Hurt in Multi-Vehicle Stevenson Ranch Crash
The city of Santa Clarita is excited to announce the winners of the 16th annual “Bike to Work Day” Challenge that took place on Thursday, May 16.
City Announces Winners of ‘Bike to Work Day’ Challenge
SACRAMENTO – The U.S. Department of Homeland Security (DHS) notified California on Wednesday that it is in full compliance with the federal REAL ID Act and regulation.
DHS: California in Full Compliance with REAL ID Regulations
The Los Angeles County Department of Public Social Services (DPSS) announces the expansion of the State of California’s CalFresh Program to now serve older adults and people with disabilities who receive Supplemental Security Income (SSI) benefits, beginning June 1, 2019.
CalFresh Expanding to Seniors, People with Disabilities Receiving SSI Benefits
LOS ANGELES – The Dodgers will hold their annual Alumni Game on Saturday, June 1, as part of Alumni Weekend presented by Security Benefit, when the club will welcome back over 30 fan-favorite players to Dodger Stadium.
More than 30 Fan Favorites to Take Part in Dodgers Alumni Weekend
SCVi, iLEAD’s founding school, will welcome Dr. Jacob Cohen, Chief Scientist at NASA Ames Research Center, to campus on Friday to kick off the school’s inaugural International Hack Into Space Competition, the school announced Thursday.
May 24: SCVi Hosts Inaugural International Hack into Space Competition
Three-hundred employees from the Los Angeles County Department of Public Social Services (DPSS) volunteered their Saturday morning over Mother’s Day weekend to inspire hope at their annual “Help the Homeless” event at the Weingart Center in downtown L.A.
County Employees Inspire Hope at Annual ‘Help the Homeless’ Event
SACRAMENTO - State Sen. Scott Wilk, representing the 21st Senate District, announced Thursday the Senate unanimously approved Senate Bill 219 (SB 219), a measure that will create a pilot program for foster youth to receive grants for extracurricular and enrichment activities.
Wilk Legislation to Create Foster Youth Pilot Program Clears State Senate
The Old Town Newhall Farmers Market will be celebrating their 4 year anniversary this Saturday, May 25, from 8:30 a.m. - 1:30 p.m. in the parking lot of the Old Town Newhall Library.
May 25: Old Town Newhall Farmers Market 4 Year Anniversary Celebration
Many people in our community have a parent or other family member who may be a veteran, who is presently deployed overseas, or who has recently returned home from active duty in the military.
June 15: Pathways to Empowerment SC Veteran & Family Mental Health Day
Robert Penalber is fairly confident that before long very little of what transpired on the course this week, or over the last four years for that matter, will be remembered.
Penalbar Misses Cut at NAIA Nationals
Well Q2 was removed from service after quarterly perchlorate sampling conducted on May 8, 2019, returned a result of 0.006 mg/L – which is the Maximum Contaminant Level (MCL), where treatment becomes necessary or a supply needs to be removed from service. Q2 is located near the Lowe’s shopping center on the west side of Bouquet Canyon, just north of the Santa Clara River.
Perchlorate Detected in Well Near Lowes Shopping Center
WASHINGTON, DC – U.S. Rep. Katie Hill serves as co-chair of the New Democrats’ Housing Task Force, which made public its goals for the 116th Congress on Wednesday. Hill serves alongside Representatives Denny Heck (D-WA) and Ben McAdams (D-UT).
Hill to Address Homelessness, Housing Shortage with New Task Force
%d bloggers like this: