Extending double-tracking and upgrading the Santa Clarita train station platform in Saugus are among the proposed infrastructure improvements to the Metrolink Antelope Valley Line approved by the Los Angeles County Metropolitan Transportation Authority on July 25.

The improvements include adding 1.6 miles of new track to double-track the stretch from the end of the Bouquet Junction bend northeast to Golden Oak Road, and widening Santa Clarita Station’s platform to accommodate the new two-track line.

Once through the environmental impact gauntlet and the final design and funding are in place, the proposed projects would cost an estimated $173.5 million and require two and a half years to 10 years complete, according to Metro officials.

The improvements would speed up Metrolink rail service and continue building passenger ridership on the 76.6-mile Antelope Valley Line, or AVL, which connects Lancaster in North Los Angeles County with Union Station in Downtown Los Angeles.

The AVL is a 76.6-mile Class 4 rail corridor route owned by Metro and used by the Southern California Regional Rail Authority, or SCRRA, running Metrolink commuter rail service between Union Station and Lancaster as well as Union Pacific Railroad for Class 1 freight service. Union Pacific trains transport goods between the ports of Los Angeles and Long Beach and distribution centers in the Antelope Valley.

The AVL has three stops in the Santa Clarita Valley — the Jan Heidt Station in Newhall; the Santa Clarita Station in Saugus; and the Via Princessa Station in Canyon Country.

Jan Heidt Newhall Metrolink Station stop

Jan Heidt Newhall Metrolink Station stop.

Right now, up to 30 Metrolink commuter trains and 12 Union Pacific freight trains per day traverse the corridor. The average passenger rail travel time between Lancaster and Union Station with 11 station stops is approximately two hours and 15 minutes.

To shorten the commute to 1 hour and 40 minutes, Metrolink currently operates two weekday roundtrip express trains from Union Station to Palmdale, with passenger stops only at the Burbank Downtown, Sylmar/San Fernando, Santa Clarita and Palmdale stations. The Antelope Valley Transit Authority also runs five round trips with bus service between Santa Clarita and Lancaster.

Metro’s long-term goals for the AVL are two-way service every 30 minutes throughout the day from any SCV station, cutting commute time between downtown Los Angeles and the Antelope Valley to an hour, and adding late-evening service.

Double-tracking, or extending railroad track sidings, would allow more train traffic to move faster along the line.

The proposed SCV improvements have been integrated into Metrolink’s 10-year Strategic Plan to significantly improve rail travel in Southern California.

Metrolink regional 10-year strategic plan

Metro officials say adding the 1.6 miles of new track in Saugus between the Bouquet Junction bend and Golden Oak Road off Soledad Canyon Road, as well as the Santa Clarita Station platform improvements, can be made on the existing railroad right-of-way without displacing any businesses or residents along the route.

Let’s take a closer look.

* * * * *

The AVL Study and Scenario 3 in the SCV
According to Metro, the Antelope Valley Line carries the Metrolink commuter rail system’s third-highest ridership, which put the AVL in the black for the first time in 2018, after years of subsidies.

AVL passengers reduce the equivalent of one lane of traffic from local freeways during peak driving hours and eliminate about 1 million weekday automobile trips per year.

Metro officials view the AVL as a model for the current Metrolink regional rail system and a key to unlocking regional mobility, as outlined in the State Rail Plan and Metrolink’s SCORE program, which it uses to prioritize projects.

Metrolink train on the Antelope Valley Line.

Seeking to build on that progress, the Metro Board commissioned the WSP consulting firm to conduct the Metrolink Antelope Valley Line Study to identify infrastructure improvements that would make service faster, more frequent and more energy-efficient.

The completed study outlined six “service scenarios,” which identified possible short-, medium- and long-term improvements in the 65.2-mile segment between the Burbank Downtown Station and the Lancaster Station.

The Board also commissioned the Mott McDonald consulting firm to produce the separate but related Los Angeles-Glendale-Burbank Study covering the remaining 11.4 miles between Burbank Downtown and Union Station.

Metro Board Directors Kathryn Barger, Ara Najarian, Paul Krekorian and Hilda L. Solis moved to adopt the AVL Study’s first three suggested scenarios and related improvement projects. The full Metro board approved the directors’ Antelope Valley Line Motion at its July 25 meeting.

“Our city of Santa Clarita will dramatically benefit from the action taken today,” said Santa Clarita Mayor Marsha McLean, who attended the Metro board meeting to urge the motion’s passage, after the board’s unanimous 11-0 vote (two voting board members were absent — Los Angeles Mayor Eric Garcetti and Long Beach Mayor Robert Garcia).

Related: Metro Backs Antelope Valley Line Study Recommendations

“Residents who regularly utilize Metrolink trains for their daily commute or recreational trips could soon have access to bi-directional service with trains running every half hour between Union Station and our city,” McLean said.

According to the approved motion, Scenario 1-3 short-term improvements would require $41.8 million in capital improvements and $4 million more in annual costs, and mid-term improvements would require approximately $175 million in capital costs, mainly for double-tracking identified in the AVL Study.

“To get these projects through environmental clearance and shovel-ready, the staff has estimated that $12.75 million is required,” the motion reads. “Shovel-ready is an important benchmark to position these projects for grant funding opportunities.”

Metrolink Antelope Valley Line improvements, with Scenario 1-3 projects highlighted in yellow. No. 6 is the Canyon-Santa Clarita Siding Extension and station platform upgrade.

Metrolink Antelope Valley Line improvements, with Scenario 1-3 projects highlighted in yellow. Circle No. 6 is the Canyon-Santa Clarita Siding Extension and station platform upgrade.

Barger, also an LA County Supervisor whose 5th District includes the Santa Clarita Valley, and a member of the North County Transportation Coalition, or NCTC, has provided funding for the environmental report and final design for Scenario 3 improvements, said Jeanet Owens, senior executive officer for Metro Regional Rail, in an email.

“The construction costs of Scenarios 2 and 3 are not yet funded,” Owens said. “The preliminary total construction cost of Scenario 3 (would be) approximately $175.3 million. We are working closely with (the NCTC) and all stakeholders to apply for state, local and federal grants to fund the construction. Looking at the glass half-full, if we were able to secure $175.3 million, we could begin construction within eight months after final design.”

Metrolink Antelope Valley Line proposed Scenarios 1-3 - four capital projects

“The study discusses the possibility of implementing Scenarios 1-3 over the course of between five and 10 years – with late-night trains and the Balboa Siding capital project being a five-year target and Scenario 3 projects being between years 5 and 10,” said David Perry, Transportation Deputy in Barger’s office.

“The intent of the Supervisor’s motion was to best position all of the Scenario 1-3 projects, so it funds all the projects to shovel-ready at the same time,” Perry said.

“That way if we are able to identify construction funds for all Scenario 3 projects, we would be able to significantly expedite them,” he said. “Theoretically, if we locked in all of the construction money in the coming months, these projects could all be completed within five years.”

Along with fast-tracking Scenarios 1-3, the Metro Board voted July 25 to prioritize the $41.8 million Balboa Tunnel Siding Project south of the SCV, which would also help make hourly commuter rail service between North LA County and Union Station possible sooner than later. This improvement was recommended in the Union Station to Burbank study.

Scenario 3 would also earmark $27.3 million for improvements to the Lancaster Metrolink Station, including new double-tracking, new storage track and platform upgrades, and $57.3 million for the Brighton-McGinley stretch out of Burbank to connect double-track segments at both ends.

The approved motion additionally calls for “the implementation of a diesel, electric, battery electric or hybrid multiple-unit train pilot program on the Antelope Valley Line” and Metro’s pursuit of grant funding focused on reducing pollution from trains, all “in support of the integrated service goals laid out in the State Rail Plan.”

“The approved Board Motion directs Metro staff to report back in October with a status report (detailing what would be necessary) to bring the capital projects included in Scenarios 1 through 3 to a ‘shovel-ready level,'” said Brian Balderrama, LA Metro’s senior director, program management/regional rail, in an email.

“‘Shovel-ready’ means the environmental study and final design will be completed,” he said, adding that the October status report should include project development plans, funding options, cash flow considerations and associated operating costs.

* * * * *

Santa Clarita Metrolink Station platform

The Santa Clarita Metrolink Station platform.

Canyon Siding Extension Project
While the AVL Study’s first two scenarios involve projects on the corridor north and south of Santa Clarita, Scenario 3’s estimated $48.8 million Canyon Siding Extension double-tracking project and the Santa Clarita Station platform expansion are within the city limits.

The siding project would extend existing double track by another 8,448 feet (1.6 miles) in Saugus, from where the double track now ends just northeast of the Bouquet Junction bend to the at-grade crossing at Golden Oak Road and Soledad Canyon Road.

The new track would parallel the existing one, following the railroad right-of-way south of Soledad Canyon Road behind businesses, the Saugus Speedway and skirting the Whittaker-Bermite site.

“The proposed improvements are assumed to be contained within the railroad right-of-way and illustrate the adjacent ownership,” Balderrama said, referring to diagrams from the preliminary plans.

Proposed Metrolink Antelope Valley Line Canyon-Santa Clarita double-tracking and platform expansion, part of Scenario 3 of the AVL Line Study approved by the Metro Board July 25.

Proposed Metrolink Antelope Valley Line Canyon-Santa Clarita double-tracking and platform expansion, part of Scenario 3 of the AVL Line Study approved by the Metro Board July 25. The purple lines represent the railroad right-of-way, and the orange line represents the new track. These images show the new track’s projected path (from left) from the Bouquet Junction bend heading northeast behind the Saugus Speedway.

Proposed Metrolink Antelope Valley Line Canyon-Santa Clarita double-tracking and platform expansion, part of Scenario 3 of the AVL Line Study approved by the Metro Board July 25.

Proposed Metrolink Antelope Valley Line Canyon-Santa Clarita double-tracking and platform expansion, part of Scenario 3 of the AVL Line Study approved by the Metro Board July 25. The purple lines represent the railroad right-of-way, and the orange line represents the new track. These images show the new track’s projected path running (from left) through the Santa Clarita Station northeast to the at-grade crossing at Golden Oak Road.

First Things First: EIR, Design
“All the proposed AVL improvements including the Canyon Siding Extension project will require an environmental study that will identify any environmental impacts including right-of-way,” Brian Balderrama, LA Metro senior director of program management for regional rail, said in an email.

Balderrama added that Metro plans to reach out to surrounding communities as well as those people and business directly adjacent to the project, before and after final approval, “to continue project collaboration, awareness and gain their support.”

But first, staff must complete those environmental reports and designs for the proposed capital projects.

“A scope of work was added that included the attached Canyon Siding Extension project concept drawings for more project detail,” Balderrama said. “Funding opportunities and cash flow considerations for the 10-year Strategic Plan will be included in the staff report to the Metro Board’s October meeting.”

* * * * *

Scenarios 4-6: A Look Down the Line
While not approved July 25, Scenarios 4-6 remain on Metro’s back burner.

“Scenarios 4 through 6 can still be considered especially as we go through the environmental study,” Owens said, adding that a timeframe for those options has not yet been determined.

Scenario 4’s proposed improvements include most of Scenario 3’s projects, plus more double-tracking and platform upgrade at the Lancaster station (eight train sets, estimated to cost roughly $30.1 million); a new 13,200-foot siding in Acton ($40.2 million); 5,808 feet of new double track between Honby (Canyon Country) and the Via Princessa Station ($26.4 million); connecting sidings at each end and converting to double-track at Hood-Saugus ($48.8 million); and 8,976 feet of new double track at Roxford in Sylmar ($42.7 million).

The Metrolink Via Princessa Station in Canyon Country is the northernmost of the three Metrolink stations in the city of Santa Clarita.

The Metrolink Via Princessa Station in Canyon Country is the northernmost of the three Metrolink stations in the city of Santa Clarita.

Scenario 5 would also call for more double-tracking and platform upgrade at the Lancaster station as in Scenario 4. Also proposed: new double track and two platform tracks at the Palmdale North station (to be integrated with high-speed rail, $127.3 million); extending existing siding at Ravena South by 13,200 feet (new double track, $56.3 million); the aforementioned 1.6-mile Canyon Santa Clarita Extension ($48.8 million) and Balboa-tunnel extension ($41.8 million); 13,200 feet of new double track in the Sheldon Street-Van Nuys Boulevard area ($67 million); and the Brighton-McGinley double-track connection (from Scenarios 3 and 4, $57.4 million).

Scenario 6’s proposed improvements are outside the SCV.

“This AVL Study is the initial study only and can be changed as we go into environmental study and design, especially as we learn more information,” Owens said.

Comment On This Story
COMMENT POLICY: We welcome comments from individuals and businesses. All comments are moderated. Comments are subject to rejection if they are vulgar, combative, or in poor taste.
REAL NAMES ONLY: All posters must use their real individual or business name. This applies equally to Twitter account holders who use a nickname.

No Comments

    Leave a Comment


    SCV NewsBreak
    LOCAL NEWS HEADLINES
    Thursday, Apr 18, 2024
    June 1: Rare Warrior 24 Race Benefiting Project Sebastian
    Join local nonprofit Project Sebastian for an exhilarating day of racing and community support at its Rare Warrior 24 race on Saturday, June 1, at Heritage Park in the heart of Santa Clarita.
    Thursday, Apr 18, 2024
    April 27: Drug Take Back Day at SCV Sheriff’s Station
    Santa Clarita Valley Sheriff's Station Station deputies will be taking part in the “DEA National Drug Take Back Day,” Saturday, April 27, from 10 a.m. to 2 p.m., in front of the SCV Sheriff’s Station, located at 26201 Golden Valley Road.
    Thursday, Apr 18, 2024
    April 30: COC Hosts Nonprofit Community Resource Fair
    The College of the Canyons Center for Civic and Community Engagement—in collaboration with COC’s Golden Z Club—invites the community to attend the Nonprofit Community Resource Fair on Tuesday, April 30.
    Keep Up With Our Facebook

    Latest Additions to SCVNews.com
    1880 - Pico Oil Spring Mine Section 2 patented by R.F. Baker and Edward F. Beale [story]
    E.F. Beale
    The Master's University men's golf team shot a 13-under 275 to finish second at the Golden State Athletic Conference Men's Golf Championships held at Briarwood Country Club in Sun City West, Ariz.
    TMU Men’s Golf Places 2nd, Women 5th at GSAC Championships
    Join local nonprofit Project Sebastian for an exhilarating day of racing and community support at its Rare Warrior 24 race on Saturday, June 1, at Heritage Park in the heart of Santa Clarita.
    June 1: Rare Warrior 24 Race Benefiting Project Sebastian
    Santa Clarita Valley Sheriff's Station Station deputies will be taking part in the “DEA National Drug Take Back Day,” Saturday, April 27, from 10 a.m. to 2 p.m., in front of the SCV Sheriff’s Station, located at 26201 Golden Valley Road.
    April 27: Drug Take Back Day at SCV Sheriff’s Station
    The College of the Canyons Center for Civic and Community Engagement—in collaboration with COC’s Golden Z Club—invites the community to attend the Nonprofit Community Resource Fair on Tuesday, April 30.
    April 30: COC Hosts Nonprofit Community Resource Fair
    College of the Canyons made quick work of visiting L.A. Valley College in a shortened 11-3 home victory that came on a day in which the program unveiled its newly named Michele Jenkins Softball Team Room during a pre-game dedication ceremony.
    Lady Cougs Outslug L.A. Valley 11-3
    For aspiring scientists at The Master’s University, taking up a student research project is no small commitment.
    Retired Professor Continues to Mentor Aspiring TMU Scientists
    The Los Angeles County Department of Public Health is warning residents not to use a Vietnamese herbal ointment called “Cao Bôi Trĩ Cây Thầu Dầu” (Castor Oil Hemorrhoid Extract) because it contains lead and can be fatal.
    Public Health Urges Residents to Avoid Vietnamese Hemorrhoid Cream
    State Superintendent of Public Instruction Tony Thurmond hosted a California Apprenticeship Summit Wednesday to raise awareness of apprenticeship opportunities and career technical education pathways that connect California’s youth to high-wage, high-growth career opportunities.
    State Apprenticeship Summit Connects Youth to High-Wage Opportunities
    College of the Canyons student-athletes Nichole Muro (softball) and Angelo Aleman (baseball) have been named the COC Athletic Department's Women's and Men's Student-Athletes of the Week for the period running April 8-13.
    COC Names Nichole Muro, Angelo Aleman Athletes of the Week
    California State Sen. Scott Wilk, R-Santa Clarita, announced Wednesday his bill improving transparency between parents and schools’ sexual education curricula passed out of the Senate Education Committee.
    Wilk’s Sex Education Transparency Bill Clears Senate Committee
    1945 - Actors Harry & Olive Carey sell Saugus ranch after 29 years; now Tesoro del Valle [story]
    Carey Ranch
    The 76.6-mile-long Antelope Valley Line has the third-highest ridership in Metrolink’s system with an estimated average of 9,000 passengers daily. However, the uneven terrain and single-tracking along the line in some areas forces trains to travel at a slower speed which results in an estimated travel time of approximately one hour between Santa Clarita and Union Station.
    Metrolink to Hold Public Meetings on AV Line Capacity, Improvements
    Team Dragon Eyes, affectionately known as TDE, is gearing up to host its highly anticipated Fifth Annual Dragonboat Festival race on Saturday, June 1 at Castaic Lake, Lower Lagoon.
    June 1: Team Dragon Eyes to Host Fifth Annual Dragonboat Festival Race
    This year marks the 20th year that the city of Santa Clarita has been hosting the annual Bike to Work Challenge. The community is invited to celebrate by riding a bike to work the week of May 13, and stopping by a pit stop on Thursday, May 16.
    Party at the Pit Stop, City Paves Way for 20th Annual Bike to Work Challenge
    Ready to take control of your financial future? Join the Los Angeles County Department of Consumer and Business Affairs Center for Financial Empowerment for the next installment in the Lunch & Learn Financial Capability Month webinar series, "Understanding Credit.
    Online Financial Workshops with County DCBA
    The Santa Clarita Valley Concert Band will perform a "Starry Might" concert at 7 p.m. on Saturday May 4. The concert, under the direction of Tim Durand, will be held at the Canyon Theatre Guild, 24242 Main St., Newhall, CA 91321.
    May 4: SCV Concert Band Presents ‘Starry Night’ at CTG
    After a record-setting 2023 combatting organized retail crime, the California Highway Patrol continues to aggressively disrupt and dismantle illegal operations throughout California.
    CHP Continues Organized Retail Crime Crackdown, Recovers $4.2M in Goods
    Celebrate Earth Day on Monday, April 22 with California State Parks at any of the 280 unique park units across the state. State Parks has numerous Earth Day-themed events planned. They include in-person activities such as guided walks and hikes, workdays and a bioblitz, as well as virtual programming with a live dive broadcast exploring the hidden world of the ocean.
    April 22: Celebrate Earth Day at California State Parks
    1930 - Telephone switchboard operator Louise Gipe, heroine of the 1928 St. Francis Dam disaster, tries & fails to kill herself over an unrequited love [story]
    Louise Gipe
    Los Angeles County Sheriff Department’s Major Crimes Bureau Detectives worked closely with Century Station Detectives after learning of a serial robbery crew committing crimes throughout Los Angeles County. 
    Serial Robbery Crew Arrested
    Join the Samuel Dixon Family Health Center for their second annual Cornhole Tournament fundraiser where all proceeds will support mental health services to anyone in need.
    May 18: Samuel Dixon Cornhole Tournament Fundraiser
    California State University, Northridge will confer honorary doctorates on four alumni, all respected leaders in their fields, at the university’s commencement ceremonies next month.
    CSUN to Confer Honorary Degrees on Business & Education Leaders, All Alumni
    On Saturday, April 20, 2024 Valencia High School Theatre will host the 104th DTASC (Drama Teachers’ Association of Southern California) Shakespeare Festival.
    April 20: 104th DTASC Shakespeare Festival at Valencia High School
    SCVNews.com