By Matthew Renda

The California State Auditor rebuked the agency in charge of implementing the state’s high-speed rail project Thursday, finding lack of planning and poor oversight has led to cost overruns plaguing the Golden State’s efforts.

“Despite being aware of risks associated with beginning construction before completing critical planning tasks, the authority began construction in 2013 – a decision that has led to contract changes, project delays, and cost overruns,” the state auditor said in a report released Thursday.

The audit prompted another round of criticism and questions about the project’s viability from state lawmakers.

“The nonpartisan state auditor has confirmed in the release of today’s audit what we have known about this disastrous rail project: flawed internal oversight that has resulted in wasted hard-earned tax dollars,” said Assemblyman Vince Fong, a Republican from Bakersfield and a frequent critic of the infrastructure project. “Billions of dollars are being poured into a project that does not resemble anything that was told to voters a decade ago.”

When California voters first passed Proposition 1A greenlighting the project in 1996, the initial price tag was pegged at about $33 billion with a completion date of 2018. The cost estimate has since climbed to $77 billion and plans now call for trains to start running in 2022.

The auditor blasted “flawed decision making and poor contract management” for the cost overruns and delays. The report also notes the California High-Speed Rail Authority must work twice as fast to bring the project to completion in the next four years or it risks losing $3.5 billion in federal grants.

The authority said it has addressed many of the shortcomings highlighted by the state auditor and plans to implement the agency’s key recommendations.

“Many of the recommendations are similar to steps we have previously identified through our own internal reviews,” said authority board member Mike Rossi. “The authority will promptly implement all of the auditor’s recommendations, as we did following the last audit that was conducted in 2012.”

The auditor took particular issue with cost oversight at the authority, saying that while 56 people were tasked with oversight of more than $5 billion in contracts, high turnover in a department that had only three full-time managers hampered the efforts. This in turn created significant problems as the authority must manage a range of different construction companies, contractors and subcontractors who are carrying out various pieces of the nation’s largest infrastructure project.

Finally, the authority has outsourced much of its contract oversight to outside consultants, but the state auditor warned such consultants may or may not have the best interests of the state and its taxpayers at heart.

The auditor said the authority must “Improve its contract management by hiring and assigning full-time and experienced contract managers who are state employees, monitoring contract managers compliance with policies and holding contract managers accountable for their performance.”

The authority has said many of the cost overruns came from difficulties in securing rights-of-way through the Central Valley, where construction is currently underway.

Rossi noted Thursday that the authority has taken recent steps to move the project forward more rapidly and efficiently under the guidance of the newly appointed CEO Brian Kelly, who came on board this past February.

The high-speed rail was championed by outgoing Governor Jerry Brown, though it remains unclear if his successor will be as enthusiastic a supporter. Governor-elect Gavin Newsom mostly dodged questions about the viability of the project on the campaign trail.

Comment On This Story
COMMENT POLICY: We welcome comments from individuals and businesses. All comments are moderated. Comments are subject to rejection if they are vulgar, combative, or in poor taste.
REAL NAMES ONLY: All posters must use their real individual or business name. This applies equally to Twitter account holders who use a nickname.

4 Comments

  1. Dave Rickmers says:

    China builds railroads really well (we taught them) and fast. I hope we spent a billion on automated track laying equipment.

  2. So Cal Guy says:

    A continued waste of tax payer money. I would really like to see Newsome’s first real big decision for California be to ditch this $77 Billion Dollar Disaster, pay back the grant money and reallocate the money to projects that are needed for California…not wanted. Brown needs to go and take his train with him. I know it’s wishful thinking…

  3. Patricia Probasco says:

    I just read that Gov. Brown did not approve a bill that would have helped clear the dead wood in our forest, giving the money to his train. Because of them unable to manage the forest, we just had the most deadly fires in California. Hope you sleep well mr. brown.

  4. Vicky Hanneman says:

    What a fiasco!! We all need to get Katie Hill involved in fighting this and get the Federal Government to stop funding Jerry Brown’s “full employment act” for his cronies!!

Leave a Comment


SCV NewsBreak
LOCAL NEWS HEADLINES
Friday, May 3, 2024
MALDEF Sues Man After Rant at Fruit Vendor in SCV
A former public school teacher who launched a racist and anti-immigrant tirade against a Santa Clarita street vendor is being sued by a Latino civil rights group for civil assault and violating California civil rights laws.
Friday, May 3, 2024
July 6: Wine in the Pines, Pine Mountain Club
The Village of Pine Mountain Club has hosted wine festivals since 2003. You can taste exciting wines from the world’s top wine-growing regions, with dozens of premier wineries to choose from on Saturday, July 6, 1-4 p.m. at Wine in the Pines.
Thursday, May 2, 2024
Biden Adds Local Acreage to Mountains Monument
The Biden administration announced Thursday that President Biden used his authority under the Antiquities Act to expand the San Gabriel Mountains National Monument near Los Angeles.
Keep Up With Our Facebook

Latest Additions to SCVNews.com
A former public school teacher who launched a racist and anti-immigrant tirade against a Santa Clarita street vendor is being sued by a Latino civil rights group for civil assault and violating California civil rights laws.
MALDEF Sues Man After Rant at Fruit Vendor in SCV
The Village of Pine Mountain Club has hosted wine festivals since 2003. You can taste exciting wines from the world’s top wine-growing regions, with dozens of premier wineries to choose from on Saturday, July 6, 1-4 p.m. at Wine in the Pines.
July 6: Wine in the Pines, Pine Mountain Club
1842 - California's first mining district established in SCV; Ygnacio del Valle, chairman [story]
Ygnacio del Valle
The American Cancer Society Relay For Life of Santa Clarita Valley will be held Saturday, May 4, 9 a.m.-9 p.m. at Central Park, with the theme “May The Cure Be With You,” a Disney/Star Wars celebration.
May 4: SCV Relay for Life ‘May the Cure Be With You’
Ten risk-taking, mid-career artists were announced Thursday as the recipients of the 2024 Herb Alpert Award in the Arts (HAAIA).
CalArts Announces 2024 Herb Alpert Award Winners
CEDAR RAPIDS, Iowa -- The Master's University men's volleyball team won their opening match of the 2024 NAIA National Championship with a 3-set win over the No. 9-seed Mount Mercy (IA) Mustangs.
Mustangs Post-Season Play Continues After First Round Win
Andrew Skerratt did not anticipate graduating with an electrical engineering degree from The Master’s University.
TMU Student Set to be School’s First Electrical Engineering Graduate
Nichole Muro was brilliant in the circle through seven shutout innings and Gigi Garcia broke the game open with a two-run double in the sixth inning as No. 15 College of the Canyons got past No. 18 Cuesta College 4-0 in its 3C2A Southern California Regional Playoffs play-in game at Whitten Field on Tuesday.
Lady Cougs Advance to Next Round in Regional Playoffs
As we kick off the new month, I am proud to reflect on the incredible growth and achievements we've witnessed over the past four months.
Message from Carlos Orozco JCI President
College of the Canyons student-athletes Sydney Tamondong (women's tennis) and Nathaniel Wilkinson (men's track and field) have been named the COC Athletic Department's Women's and Men's Student-Athletes of the Week for the period running April 22-27.
COC Names Sydney Tamondong, Nathaniel Wilkinson Athletes of the Week
With spring in full effect, now is the best time to hit the trails and enjoy the natural scenery of Santa Clarita.
Ken Striplin | Hit the Trails During Santa Clarita Bike Challenge
The Biden administration announced Thursday that President Biden used his authority under the Antiquities Act to expand the San Gabriel Mountains National Monument near Los Angeles.
Biden Adds Local Acreage to Mountains Monument
The Tony Award nominations, which honor excellence in live Broadway theater, were announced on April 30 with lighting designer and California Institute of the Arts alum Brandon Stirling Baker (Theater BFA 10) among the nominees.
CalArts Alum Earns Tony Nomination
The Master’s University will be well-represented during the International Christian Film Festival in Orlando, Florida, which is running now through May 4.
TMU Film Earns ‘Best Picture’ Nod at International Christian Film Festival
1884 - McCoy & Everette Pyle discover important Tataviam Indian artifacts in Bowers Cave (Val Verde) [story]
Bowers Cave artifacts
The Los Angeles County, Department of Public Social Services, and the Department of Public Health’s  CalFresh Healthy Living Program have launched the annual CalFresh Awareness Month campaign to remove barriers associated with applying for food assistance.
May is CalFresh Awareness Month
Ekklesia Meta Church, a non-denominational institution founded by Pastor Carthel Towns, is proud to announce the grand opening of its Community Closet in Santa Clarita. 
May 4: Ekklesia Meta Church to Launch Community Closet in Santa Clarita
College of the Canyons captured a 13th straight Western State Conference Championship on Monday, April 29 at Knollwood Country Club, after a 36-hole tourney that saw all six players finish in the top-10 of the field's individual standings and send the Cougars to another 3C2A Southern California Regional Championship event.
Canyons Wins 13th Consecutive WSC Title
The Los Angeles County Department of Public Health cautions residents who are planning to visit the below Los Angeles County beaches to avoid swimming, surfing, and playing in ocean waters:
Ocean Water Warning For May 1
The cheers will be heard blocks away later this month as more than 11,000 graduating students cross the stage in front of California State University, Northridge’s iconic University Library as CSUN celebrates its 2024 commencement.
CSUN to Celebrate the Class of 2024 with Series of Ceremonies
Thanks to the community's support, E.C. Loomis Insurance Associates has officially awarded a $10,000 donation to The American Cancer Society, a nonprofit organization dedicated to saving lives, celebrating lives, and leading the fight for a world without cancer.
The American Cancer Society Awarded $10,000
Imagine a day where barriers dissolve and possibilities unfold, a day dedicated to celebrating diversity and fostering inclusivity.
Cameron Smyth:  Free To Be Me at West Creek Park
The final Business Property Statement deadline is approaching fast, with payments need by May 7 to avoid penalties. 
May 7: Assessor Reminds Businesses as Last BPP Deadline Nears
The Santa Clarita Valley Economic Development Corporation teamed up with the city of Santa Clarita, College of the Canyons, L.A. County's America's Job Center of California and the Chamber of Commerce to host the fourth Santa Clarita Valley job fair.
Fourth SCV Job Fair Draws Biggest Crowd Yet
SCVNews.com