Staff recommendation before the Board of Supervisors Tuesday, Oct. 20, 2015:

 

 

This action is to approve a change in work and the increased contract amount for a construction contract for State Route 126/Commerce Center Drive Interchange in the unincorporated community of Castaic.

 

IT IS RECOMMENDED THAT THE BOARD:

Find that the requested change in work related to construction of a cast-in-place, prestressed reinforced concrete bridge, asphalt concrete pavement, Portland cement concrete pavement on base material, reinforced concrete barriers, soil-cement bank stabilization, drainage facilities, traffic signals, intelligent transportation systems; with an increase in the construction contract amount of

$556,000; will have no significant effect on the environment and approve the change and increased contract amount for Project ID No. RDC0014507 – State Route 126/Commerce Center Drive Interchange; for revising pavement structural sections in the unincorporated community of Castaic, performed by C.A. Rasmussen, Inc.

 

 

PURPOSE/JUSTIFICATION OF RECOMMENDED ACTION

The purpose of the recommended action is to obtain approval from the Board for the change in this construction contract in support of the timely completion of the project while avoiding delays and the potential for claims.

 

The Honorable Board of Supervisors 10/20/2015

Page 2

 

Enclosed for the Board’s approval is a description of change in work, the necessary time extension, and the cost which is in excess of the Director of Public Works’ delegated limit required to complete the project.

 

Implementation of Strategic Plan Goals

The Countywide Strategic Plan directs the provisions of Operational Effectiveness/Fiscal Sustainability (Goal 1) and Integrated Services Delivery (Goal 3). Approval of this change will provide improved infrastructure to better serve the public and enhance the quality of life in the affected community.

 

FISCAL IMPACT/FINANCING

 

This change in work will have no impact to the County General Fund.

 

Project ID No. RDC0014507, with an increase in the construction contract amount of $556,000, is included in the Fifth Supervisorial District’s Transportation Improvement Program in the Road Fund Fiscal Year 2015-16 Budget.

 

If this change in work is not approved, contract completion will be delayed and increased costs incurred.

 

FACTS AND PROVISIONS/LEGAL REQUIREMENTS

 

The contract for the construction of this improvement was awarded on April 30, 2013, to a contractor with the lowest responsive bid in accordance with the State Public Contract Code and the Board’s directives.

 

ENVIRONMENTAL DOCUMENTATION

 

This change in work as described above and in the enclosure does not change any conditions which resulted in the original environmental findings.

 

CONTRACTING PROCESS

 

The contract provides that the contractor be compensated for the work resulting from a change to the original plans and specifications or changed conditions encountered during the course of construction. The cost is based on contract unit prices, time and materials, or negotiated under the provisions of the contract specifications.  The method for arriving at the cost of the change is included in the enclosure.

 

IMPACT ON CURRENT SERVICES (OR PROJECTS)

 

Approval of the requested change by the Board will ensure the timely completion of work under the contract and result in complete and usable facilities.

 

The Honorable Board of Supervisors 10/20/2015

Page 3

CONCLUSION

 

Please return one adopted copy of this letter to the Department of Public Works, Construction Division.

 

 

 

 

CHANGE IN WORK

October 20, 2015

 

 

PROJECT ID NO. RDC0014507 – State Route 126/Commerce Center Drive Interchange, (in the unincorporated community of Castaic), Supervisorial District 5 Contractor:  C.A. Rasmussen, Inc.

 

Project Description:

 

Construction of a cast-in-place, prestressed reinforced concrete bridge, asphalt  concrete pavement, Portland cement concrete pavement on base material, reinforced concrete barriers, soil-cement bank stabilization, drainage facilities, traffic signals, intelligent transportation systems, and the performance of other appurtenant work.

 

Change in Work:

 

Revise pavement structural sections                                                                    $556,000.00 Description of Change:

Due to the unavailability of suitable material at the mandatory borrow site, it is  necessary to revise the structural section for hot mix asphalt pavement for the roadway widening, shoulders, and ramps. A portion of the change in work was previously approved under delegated authority in the amount of $180,000 to stabilize the  subgrade. In order to complete the work, an additional 556,000 is  needed.  This exceeds the Director’s delegated authority limit and requires the Board’s approval.

 

The cost for this work is based on Section 3 of the contract specifications. No additional working days will be required because of this change.

Financial Information:

 

Sufficient funds for this project are included in the Fifth Supervisorial District’s Transportation Improvement Program in the Road Fund Fiscal Year 2015-16 Budget. The Road Fund will ultimately be reimbursed with Westside Bridge and Major Thoroughfare Construction Fee funds as fees are collected.

Comment On This Story
COMMENT POLICY: We welcome comments from individuals and businesses. All comments are moderated. Comments are subject to rejection if they are vulgar, combative, or in poor taste.
REAL NAMES ONLY: All posters must use their real individual or business name. This applies equally to Twitter account holders who use a nickname.

No Comments

    Leave a Comment


    LOS ANGELES COUNTY HEADLINES
    Thursday, Dec 18, 2025
    Santa Clarita Valley residents need to put down the yule log and refrain from all residental wood burning fires on Friday, Dec. 19.
    Wednesday, Dec 17, 2025
    The Los Angeles County Sheriff’s Department  Forensic In-Patient Step Down program’s success has led to an annual graduation that not only celebrates the participants for the progress they have made in the program but also acknowledges the department’s commitment to excellence in custody operations. 
    Wednesday, Dec 17, 2025
    The Los Angeles County Sheriff’s Department was awarded a $134,000 grant from the California Office of Traffic Safety
    Tuesday, Dec 16, 2025
    The Greater Lost Angeles Homeless Count (Jan. 20-22) is still in need of volunteers.
    Monday, Dec 15, 2025
    The Los Angeles County Sheriff's Department has issued a statement regarding the Terrorist Attack in Australia on the first night of Hanukkah.

    Keep Up With Our Facebook
    Latest Additions to SCVNews.com
    1970 - Snow day in Santa Clarita Valley [photos]
    Saugus train station
    Do you have a passion for swimming and a desire to make an impact in your community? The city of Santa Clarita is seeking individuals with strong customer service skills and a commitment to community engagement to join its lifeguard team.
    Applications Are Open for the Summer 2026 Lifeguard Season
    Santa Clarita Valley residents need to put down the yule log and refrain from all residental wood burning fires on Friday, Dec. 19.
    Dec. 19: No Burn Day Alert Issued for SCV, South Coast Air Basin
    U.S. Rep. George Whitesides (D-Aqua Dulce), announced the winners of the 2025 Congressional App Challenge for California’s 27th Congressional District: the “MathViz” team led by local Academy of the Canyons student, Gautham Korrapati.
    Whitesides Announces 2025 Congressional App Challenge SCV Winners
    The Mardi Gras Madness 1K/5K/10K, set for March 1, in Santa Clarita, is more than a race, it’s a celebration of health, community and giving back. Now through Wednesday, Dec. 24, take $10 OFF race registration with promo code WINTER10 at checkout.
    March 1: JCI Santa Clarita Holds Mardi Gras Madness 1K/5K/10K Runs
    Theatre Extempore will present the all time classic musical The Fantasticks, 8-10 p.m. Jan. 9-11. 15-18 at The MAIN.
    Jan. 9: Premiere of ‘The Fantasticks’ Presented by Theatre Extempore
    West Ranch High School senior Braulio Castillo (17) never did any long-distance running before high school, but what he has accomplished in that demanding discipline since taking it up is impressive. And, so far his senior year, it is phenomenal.
    West Ranch Runner Going the Distance
    Powerlab Studio will hold its grand opening and ribbon cutting 4:30-5 p.m. Thursday, Jan. 8 at 28110 Newhall Ranch Road, Valencia, CA 91355.
    Jan 8: Powerlab Studio Grand Opening, Ribbon Cutting
    B2 Entertainment will have a Cookies With Santa event, 3-5 p.m. Sunday, Dec. 21 at 21516 Golden Triangle Road, Santa Clarita, CA 91350.
    Dec. 21: Cookies With Santa at MB2 Entertainment
    The College of the Canyons soccer programs will be hosting 'Friday Night Footy,' small-sided pick-up games, running on Friday evenings Jan. 2 through June 26 at the COC Soccer Facility.
    Jan. 2-June 26: Cougars Soccer Programs to Host ‘Friday Night Footy’
    College of the Canyons sophomore pitcher Nichole Muro will continue her academic and athletic career at Cumberland University after signing with the Phoenix softball program.
    Muro Signs with Cumberland University Softball Program
    College of the Canyons men's basketball won its fourth straight contest in an 80-72 affair at Napa Valley College on Monday afternoon, Dec. 15 as freshman Julius Washington led all scorers with 20 points.
    Cougars Win Fourth Straight 80-72 at Napa Valley
    Canyons women's basketball snapped a five-game losing streak with a 60-44 win over Diablo Valley College during the final day of action at the Napa Valley Storm Surge tournament on Saturday, Dec. 13.
    Canyons Finishes Tourney Weekend with 60-44 Win Over Diablo Valley
    1929 - Swift justice: Thomas Vernon sentenced to life in prison for Saugus train derailment & robbery 1 month earlier [story]
    Tom Vernon
    The Newhall School District Board of Trustees met on Tuesday, Dec. 16 for its annual organiational meeting.
    Newhall School Board Elects Rachelle Haddoak 2026 Board President
    The Los Angeles County Sheriff’s Department  Forensic In-Patient Step Down program’s success has led to an annual graduation that not only celebrates the participants for the progress they have made in the program but also acknowledges the department’s commitment to excellence in custody operations. 
    LASD Custody Division Honors Inmates on the Path of Recovery and Success
    The study of bones from the largest collection of Neandertal remains in Northern Europe has revealed evidence of selective cannibalism targeting Neandertal females and children between 41,000 and 45,000 years ago.
    Research by CSUN Prof Finds Neandertal Selective Cannibalism 45,000 Years Ago
    State Superintendent of Public Instruction Tony Thurmond today announced that registration is open for the second annual School Leadership to End Hate Winter Institute, co-hosted by the California Department of Education and the California Teachers Collaborative for Holocaust and Genocide Education.
    State Education Dept. to Address Rising Antisemitism, Hate
    The Los Angeles County Sheriff’s Department was awarded a $134,000 grant from the California Office of Traffic Safety
    LASD Crime Lab Awarded Grant to Bolster Testing for DUI Cases
    Southern California’s iconic Joshua trees are in bloom, and California State University, Northridge’s environmental biologists are asking the public’s help in figuring out why and what it means for the trees’ future.
    CSUN Researchers Call for Public’s Help in Documenting Joshua Trees’ Surprise Out-of-Season Bloom
    The California Department of Motor Vehicles today issued its decision in the Tesla administrative case, adopting the administrative law judge’s proposed decision
    DMV Finds Tesla Violated California State Law With ‘Autopilot’ Terms
    Starting January 1, 2026, Santa Clarita Transit is launching Fare Capping, meaning once riders hit the daily or weekly cap, the rest of their local rides are free.
    Santa Clarita Transit Launches Fare Capping Beginning January 2026
    The University Library at California State University, Northridge has completed the processing and cataloging of the Los Angeles Jewish Federation Community Relations Committee (CRC) Archives, spanning from 1921 to 2000, providing researchers and the public access to one of the most comprehensive archives documenting the Jewish community’s role in combating antisemitism, fascism and discrimination in Southern California and beyond.
    CSUN University Library Announces Completion of Jewish Community Archives Processing (1921–2000)
    1839 - Judge John F. Powell born in Galway, Ireland [story]
    John F. Powell
    SCVNews.com