By Matthew Renda

The California State Auditor rebuked the agency in charge of implementing the state’s high-speed rail project Thursday, finding lack of planning and poor oversight has led to cost overruns plaguing the Golden State’s efforts.

“Despite being aware of risks associated with beginning construction before completing critical planning tasks, the authority began construction in 2013 – a decision that has led to contract changes, project delays, and cost overruns,” the state auditor said in a report released Thursday.

The audit prompted another round of criticism and questions about the project’s viability from state lawmakers.

“The nonpartisan state auditor has confirmed in the release of today’s audit what we have known about this disastrous rail project: flawed internal oversight that has resulted in wasted hard-earned tax dollars,” said Assemblyman Vince Fong, a Republican from Bakersfield and a frequent critic of the infrastructure project. “Billions of dollars are being poured into a project that does not resemble anything that was told to voters a decade ago.”

When California voters first passed Proposition 1A greenlighting the project in 1996, the initial price tag was pegged at about $33 billion with a completion date of 2018. The cost estimate has since climbed to $77 billion and plans now call for trains to start running in 2022.

The auditor blasted “flawed decision making and poor contract management” for the cost overruns and delays. The report also notes the California High-Speed Rail Authority must work twice as fast to bring the project to completion in the next four years or it risks losing $3.5 billion in federal grants.

The authority said it has addressed many of the shortcomings highlighted by the state auditor and plans to implement the agency’s key recommendations.

“Many of the recommendations are similar to steps we have previously identified through our own internal reviews,” said authority board member Mike Rossi. “The authority will promptly implement all of the auditor’s recommendations, as we did following the last audit that was conducted in 2012.”

The auditor took particular issue with cost oversight at the authority, saying that while 56 people were tasked with oversight of more than $5 billion in contracts, high turnover in a department that had only three full-time managers hampered the efforts. This in turn created significant problems as the authority must manage a range of different construction companies, contractors and subcontractors who are carrying out various pieces of the nation’s largest infrastructure project.

Finally, the authority has outsourced much of its contract oversight to outside consultants, but the state auditor warned such consultants may or may not have the best interests of the state and its taxpayers at heart.

The auditor said the authority must “Improve its contract management by hiring and assigning full-time and experienced contract managers who are state employees, monitoring contract managers compliance with policies and holding contract managers accountable for their performance.”

The authority has said many of the cost overruns came from difficulties in securing rights-of-way through the Central Valley, where construction is currently underway.

Rossi noted Thursday that the authority has taken recent steps to move the project forward more rapidly and efficiently under the guidance of the newly appointed CEO Brian Kelly, who came on board this past February.

The high-speed rail was championed by outgoing Governor Jerry Brown, though it remains unclear if his successor will be as enthusiastic a supporter. Governor-elect Gavin Newsom mostly dodged questions about the viability of the project on the campaign trail.

Comment On This Story
COMMENT POLICY: We welcome comments from individuals and businesses. All comments are moderated. Comments are subject to rejection if they are vulgar, combative, or in poor taste.
REAL NAMES ONLY: All posters must use their real individual or business name. This applies equally to Twitter account holders who use a nickname.

4 Comments

  1. Dave Rickmers says:

    China builds railroads really well (we taught them) and fast. I hope we spent a billion on automated track laying equipment.

  2. So Cal Guy says:

    A continued waste of tax payer money. I would really like to see Newsome’s first real big decision for California be to ditch this $77 Billion Dollar Disaster, pay back the grant money and reallocate the money to projects that are needed for California…not wanted. Brown needs to go and take his train with him. I know it’s wishful thinking…

  3. Patricia Probasco says:

    I just read that Gov. Brown did not approve a bill that would have helped clear the dead wood in our forest, giving the money to his train. Because of them unable to manage the forest, we just had the most deadly fires in California. Hope you sleep well mr. brown.

  4. Vicky Hanneman says:

    What a fiasco!! We all need to get Katie Hill involved in fighting this and get the Federal Government to stop funding Jerry Brown’s “full employment act” for his cronies!!

Leave a Comment


SCV NewsBreak
LOCAL NEWS HEADLINES
Thursday, Dec 25, 2025
SCV Sheriff’s Station Issues Traffic Alert on Soledad Canyon Road
The Santa Clarita Valley Sheriff's Station has issued the following traffic alerts: Due to heavy rains, the westbound right lane is closed on Soledad Canyon Road between Camp Plenty Road and Langside Avenue.
Thursday, Dec 25, 2025
Fostering Youth Independence Hosts Holiday PJ Party
Fostering Youth Independence’s recent Charlie Brown Holiday party was attended by dozens of local foster youth and their volunteer Allies.
Thursday, Dec 25, 2025
NWS Issues Flood Watch for SCV Through Friday
The National Weather Service as issued the following alerts for the Santa Clarita Valley. Flood Watch until Dec. 26, 4 p.m. PST, High Wind Warning until Dec. 25, 3 p.m. PST.
Keep Up With Our Facebook

Latest Additions to SCVNews.com
1873 - Vasquez gang raids Kingston in (now) Kings County; ties up townspeople, makes off with $2,500 in cash and jewels [story]
Kingston
The Santa Clarita Valley Sheriff's Station has issued the following traffic alerts: Due to heavy rains, the westbound right lane is closed on Soledad Canyon Road between Camp Plenty Road and Langside Avenue.
SCV Sheriff’s Station Issues Traffic Alert on Soledad Canyon Road
Fostering Youth Independence’s recent Charlie Brown Holiday party was attended by dozens of local foster youth and their volunteer Allies.
Fostering Youth Independence Hosts Holiday PJ Party
The National Weather Service as issued the following alerts for the Santa Clarita Valley. Flood Watch until Dec. 26, 4 p.m. PST, High Wind Warning until Dec. 25, 3 p.m. PST.
NWS Issues Flood Watch for SCV Through Friday
1852 - Acton gold mine owner & California Gov. Henry Tifft Gage born in New York [story]
Henry Gage
Los Angeles County Supervisor Kathryn Barger is urging residents to remain vigilant as a powerful storm system moves through Los Angeles County, bringing periods of heavy rain and rapidly changing conditions.
Barger Urges Residents to Stay Alert, Follow Evacuation Orders
Thirteen suspects were arrested, and more than $800,000 in stolen merchandise was recovered following a coordinated, multi-agency operation targeting an organized retail theft network operating across Northern California.
CHP Makes Multiple Arrests in Organized Retail Theft Investigation
The California State Transportation Agency today announced a new joint effort by two of its departments, the Department of Motor Vehicles and California Highway Patrol, to curb excessive speeding and prevent deadly crashes.
Pilot Program to Crack Down on Extreme Speeding
The city of Santa Clarita invites the community to heat up the holiday season at the Holiday Spice Salsa Edition on Saturday, Dec. 27, at the Canyon Country Community Center, located at 18410 Sierra Highway Santa Clarita, CA 91351.
Dec. 27: Holiday Spice Salsa Edition at Canyon Country Community Center
1965 - Signal newspaper owner Scott Newhall shows up for a duel (of words) with rival Canyon Country newspaper publisher Art Evans, who no-shows and folds his paper soon after [story]
headline
As winter storms enter Los Angeles County, the Los Angeles County Department of Animal Care and Control urges pet owners to take necessary precautions in light of the significant storms expected to last for five days.
DACC Urges Pet Owners to Prioritize Safety Ahead of Storm
Brayden Miner scored 31 points and Rylan Starr had 24 as The Master's University men's basketball team crushed Bethesda University 145-59 The MacArthur Center.
Season’s Best Offensive Performance Leads TMU Over Bethesda
From surprise Santa arrivals to stacks of gifts waiting for young hands, the Boys & Girls Club of Santa Clarita Valley delivered holiday cheer on a large scale this season, reaching hundreds of children and teens throughout the Santa Clarita Valley, including Clubhouses in Canyon Country, Newhall, Val Verde and Castaic.
Boys & Girls Club of Santa Clarita Valley Spreads Holiday Cheer
Princess Cruises, headquartered in Santa Clarita, embraced a cherished maritime tradition in a uniquely festive way, celebrating a symbolic christening of its Rose Parade float with a ceremonial break of a bottle of Pantalones Organic Tequila.
Princess Cruises Christens Star Princess Tournament of Roses Float
The Golden Globes have ushered in awards season with the announcement of the 2026 nominees across 28 categories. Among this year’s contenders is Pixar’s "Elio," which earned a nomination for Best Motion Picture – Animated.
CalArtian-Directed ‘Elio’ Nominated for 2026 Golden Globe
The National Weather Service has issued a "Hazardous Weather" warning for the Santa Clarita Valley and Southern California.
NWS Issues Flood, High Wind Warnings for SCV, Southland
Detectives from the Los Angeles County Sheriff’s Department Missing Persons Unit are asking for the public’s help locating at-Risk missing person Drew Barrick Russell.
LASD Asks for Help Locating Missing Santa Clarita Man
1997 - Five bodies found during grading of Northlake development in Castaic; determined to be Jenkins graveyard [story]
reburial
Old Town Newhall Public Library will host "Spice Travels," Friday, Jan. 2, 9:15-9:30 a.m. at 24500 Main St., Santa Clarita, CA 91321.
Jan. 2: Explore Global Cuisine with ‘Spice Travels ‘ at Newhall Library
The California Highway Patrol encourages the public to “brake” the habit of speeding this holiday season. The CHP will launch a Holiday Enforcement Period starting at 6:01 p.m. on Wednesday, Dec. 24, and ending at 11:59 p.m. on Thursday, Dec. 25.
Dec. 24-25: CHP Launches Holiday Enforcement Period
Volunteers are needed to help clear brush and restore the tread from the existing lower Gates and Twister trails 8 a.m.-noon Saturday, Dec. 27.
Dec. 27: Volunteers Needed for SCV Trail Users Workday
Join InfluenceHER's "Redefining Happiness, a Candid Conversation for the Modern Woman," 4-6 p.m., Friday, Jan. 16 at the Venue Valencia.
Jan. 16: InfluenceHER- Redefining Happiness, A Candid Conversation for the Modern Woman
The Santa Clarita Public Library system has announced that all library branches will close at 1 p.m. on Christmas Eve, Wednesday, Dec. 24, and remain closed on Christmas Day, Thursday, Dec. 25, in observance of Christmas.
Santa Clarita Public Library Holiday Hours
SCVNews.com