By Matthew Renda

The California State Auditor rebuked the agency in charge of implementing the state’s high-speed rail project Thursday, finding lack of planning and poor oversight has led to cost overruns plaguing the Golden State’s efforts.

“Despite being aware of risks associated with beginning construction before completing critical planning tasks, the authority began construction in 2013 – a decision that has led to contract changes, project delays, and cost overruns,” the state auditor said in a report released Thursday.

The audit prompted another round of criticism and questions about the project’s viability from state lawmakers.

“The nonpartisan state auditor has confirmed in the release of today’s audit what we have known about this disastrous rail project: flawed internal oversight that has resulted in wasted hard-earned tax dollars,” said Assemblyman Vince Fong, a Republican from Bakersfield and a frequent critic of the infrastructure project. “Billions of dollars are being poured into a project that does not resemble anything that was told to voters a decade ago.”

When California voters first passed Proposition 1A greenlighting the project in 1996, the initial price tag was pegged at about $33 billion with a completion date of 2018. The cost estimate has since climbed to $77 billion and plans now call for trains to start running in 2022.

The auditor blasted “flawed decision making and poor contract management” for the cost overruns and delays. The report also notes the California High-Speed Rail Authority must work twice as fast to bring the project to completion in the next four years or it risks losing $3.5 billion in federal grants.

The authority said it has addressed many of the shortcomings highlighted by the state auditor and plans to implement the agency’s key recommendations.

“Many of the recommendations are similar to steps we have previously identified through our own internal reviews,” said authority board member Mike Rossi. “The authority will promptly implement all of the auditor’s recommendations, as we did following the last audit that was conducted in 2012.”

The auditor took particular issue with cost oversight at the authority, saying that while 56 people were tasked with oversight of more than $5 billion in contracts, high turnover in a department that had only three full-time managers hampered the efforts. This in turn created significant problems as the authority must manage a range of different construction companies, contractors and subcontractors who are carrying out various pieces of the nation’s largest infrastructure project.

Finally, the authority has outsourced much of its contract oversight to outside consultants, but the state auditor warned such consultants may or may not have the best interests of the state and its taxpayers at heart.

The auditor said the authority must “Improve its contract management by hiring and assigning full-time and experienced contract managers who are state employees, monitoring contract managers compliance with policies and holding contract managers accountable for their performance.”

The authority has said many of the cost overruns came from difficulties in securing rights-of-way through the Central Valley, where construction is currently underway.

Rossi noted Thursday that the authority has taken recent steps to move the project forward more rapidly and efficiently under the guidance of the newly appointed CEO Brian Kelly, who came on board this past February.

The high-speed rail was championed by outgoing Governor Jerry Brown, though it remains unclear if his successor will be as enthusiastic a supporter. Governor-elect Gavin Newsom mostly dodged questions about the viability of the project on the campaign trail.

Comment On This Story
COMMENT POLICY: We welcome comments from individuals and businesses. All comments are moderated. Comments are subject to rejection if they are vulgar, combative, or in poor taste.
REAL NAMES ONLY: All posters must use their real individual or business name. This applies equally to Twitter account holders who use a nickname.

4 Comments

  1. Dave Rickmers says:

    China builds railroads really well (we taught them) and fast. I hope we spent a billion on automated track laying equipment.

  2. So Cal Guy says:

    A continued waste of tax payer money. I would really like to see Newsome’s first real big decision for California be to ditch this $77 Billion Dollar Disaster, pay back the grant money and reallocate the money to projects that are needed for California…not wanted. Brown needs to go and take his train with him. I know it’s wishful thinking…

  3. Patricia Probasco says:

    I just read that Gov. Brown did not approve a bill that would have helped clear the dead wood in our forest, giving the money to his train. Because of them unable to manage the forest, we just had the most deadly fires in California. Hope you sleep well mr. brown.

  4. Vicky Hanneman says:

    What a fiasco!! We all need to get Katie Hill involved in fighting this and get the Federal Government to stop funding Jerry Brown’s “full employment act” for his cronies!!

Leave a Comment


SCV NewsBreak
LOCAL NEWS HEADLINES
Thursday, Sep 19, 2024
COC Receives $300,000 NASA Grant to Expand Student Access to STEM Fields
The College of the Canyons Aerospace and Science Team has received a $300,000 grant from NASA’s Mentoring and Opportunities in STEM with Academic Institutions for Community Success program.
Thursday, Sep 19, 2024
Sept. 26: Community Invited to David March Park Expansion Groundbreaking
One of the city of Santa Clarita community’s most cherished parks, David March Park is set to expand, Thursday, Sept. 26, at 10 a.m., 28310 North Via Joyce Drive, Santa Clarita, CA 91350 with a groundbreaking ceremony.
Thursday, Sep 19, 2024
COC Board of Trustees Appoints Carlos Guerrero to Area 5 Seat
The Santa Clarita Community College District Board of Trustees appointed Carlos Guerrero to fill the board seat in Area 5, effective immediately, at its special Wednesday, Sept. 18 meeting.
Keep Up With Our Facebook

Latest Additions to SCVNews.com
1954 - C-46 cargo plane crashes at Saugus Drunk Farm; Civil Air Patrol chaplains parachute to safety [story]
chaplains
The College of the Canyons Aerospace and Science Team has received a $300,000 grant from NASA’s Mentoring and Opportunities in STEM with Academic Institutions for Community Success program.
COC Receives $300,000 NASA Grant to Expand Student Access to STEM Fields
Bring along a furry friend to the Santa Clarita Child & Family Center's Purple Walk Domestic Violence Awareness 5K on Saturday, Oct. 5 from 8-11 a.m. at the Center’s main facility 21545 Centre Pointe Parkway, Santa Clarita, CA 91350.
Oct. 5: 5K Purple Walk Dogs Against Domestic Violence
Written and directed by Braddon Mendelson, produced by Heather Mendelson, and co-produced by Olive Branch Theatricals and Noisivision Studios, "Provenance" will take stage at the The MAIN, 24266 Main Street, Santa Clarita, CA 91321, Friday through Sunday, Sept. 27-29.
Sept. 27-29: Braddon Mendelson to Present ‘Provenance’ at The MAIN
The Master's women's volleyball team opened Great Southwest Athletic Conference play on the road in Prescott, Ariz. on Wednesday, Sept. 18, defeating the Embry-Riddle Aeronautical University Eagles in straight sets 28-26, 25-22, 25-18.
TMU Women’s Volleyball Opens Conference Play with Road Win
College of the Canyons freshman Sahya Kitabatake shot a two-under-par round of 70 to tie for medalist honors while helping the Cougars place fourth at the Western State Conference tournament at Sterling Hills Golf Club in Camarillo on Monday, Sept. 16.
Kitabatake Medals, Canyons Women Take Fourth at Sterling Hills Golf Club
One of the city of Santa Clarita community’s most cherished parks, David March Park is set to expand, Thursday, Sept. 26, at 10 a.m., 28310 North Via Joyce Drive, Santa Clarita, CA 91350 with a groundbreaking ceremony.
Sept. 26: Community Invited to David March Park Expansion Groundbreaking
SRD Straightening Reigns, a therapeutic organization offering equine assisted psychotherapy, has been awarded $278,870 from the California State budget to improve mental health services.
California Awards $278,870 in Funding to SRD Straightening Reins
The Santa Clarita Community College District Board of Trustees appointed Carlos Guerrero to fill the board seat in Area 5, effective immediately, at its special Wednesday, Sept. 18 meeting.
COC Board of Trustees Appoints Carlos Guerrero to Area 5 Seat
California Institute of the Arts alums Alyssa Dressman Lehner and Clara Plestis captured Emmy Awards at the 76th Primetime Creative Arts Emmy Awards.
Two Calartians Win 2024 Creative Arts Emmy Awards
Valencia High School's Choir will hold a fall concert, "Broadway, Movies & Media" at 7 p.m., Thursday, Sept. 26 at 7 p.m. and Friday, Sept. 27, 7 p.m. at the Saugus High School Theatre, 21900 Centurion Way, Santa Clarita, CA 91350.
Sept. 26-27: Valencia High Choir Presents Fall Concert ‘Broadway, Movies & Media’
As my wife, Virginia, and I stroll through our magnificent city, we admire the beautiful paseos and the expansive open spaces, but what really catches our eye, is the diverse works of art at every turn.
Bill Miranda | Santa Clarita Arts, a Journey Through Creativity
The California Department of Public Health is encouraging all Californians to get vaccinated this season to protect themselves and loved ones from respiratory viruses.
CDPH: Stay Up to Date on Vaccines
The Friends of Santa Clarita Public Library in collaboration with Santa Clarita Valley Libraries will have a silent Book Auction beginning at 9 a.m. Monday, Sept. 30, through 10 a.m. on Monday, Oct. 7.
Sept. 30: Public Libraries to Host Silent Book Auctions
1863 - Gen. Edward F. Beale loans money to A.A. Hudson and Oliver P. Robbins to erect toll house in Newhall Pass [story]
toll house
The Counties of Los Angeles and San Bernardino today announced the opening of multiple joint Local Assistance Centers to assist residents impacted by the Bridge and Line Fires.
Joint Assistance Centers Open for Residents Impacted by Bridge, Line Fires
Valencia Gynecology Associates, owned by longtime Santa Clarita Valley OB-GYN physician Don Nishiguchi, MD, has joined the Henry Mayo Newhall Hospital network. 
Valencia Gynecology Assoc. Joins Henry Mayo Network
JCI Santa Clarita is proud to announce the upcoming Veteran’s Resource Fair, scheduled to take place on Sept. 21 at William S. Hart Park. 
Sept. 21: JCI Invites All Veterans to Upcoming Resource Fair
A "friendies" field tournament  is being  hosted by the Saugus Instrumental Music program, with support from Valencia High, later this month. 
Sept. 21: All Valley Showcase Comes to Valencia High
Public, member-supported 88.5 FM The SoCal Sound, Southern California’s leading Triple-A (adult album alternative) format radio station has announced the lineup for its inaugural “Year-End Bash” taking place on Saturday, Dec. 7.
Dec. 7: CSUN Owned 88.5-FM The SoCal Sound Announces “Year End Bash” Lineup featuring Ben Gibbard
The Master's University cross-country teams continued their successful 2024 campaigns with strong finishes at the BIOLA Invitational on Friday, Sept. 13 at Craig Regional Park in Fullerton, Calif.
TMU Women Win, Men Place Second at XC Invitational
Sheriff’s Department Announces New Law Enforcement Gang Policy
LASD Announces New Policy on Law Enforcement Gangs
The biology department at California State University, Northridge has stayed committed to promoting STEM research carried out by K-12 students and teachers in the Los Angeles Unified School District.
CSUN Student Research Journal Celebrates 28 Years of Inspiring Scientific Imagination
Did you know the SCVEDC has an interactive, online tool that provides themed virtual tours of the amazing features the community has to offer? 
SCVEDC Offers Virtual Business Tours of the Santa Clarita Valley
SCVNews.com