SACRAMENTO – With new leadership in place, the California High-Speed Rail Authority today released the Draft 2018 Business Plan that transparently acknowledges the project’s challenges and outlines a sensible path forward that will continue to put thousands of Californians to work building the nation’s first high-speed rail system.
“The Draft 2018 Business Plan presents a strategy to implement the nation’s first truly high-speed rail system in the face of challenges that projects around the world of similar magnitude and complexity have faced and successfully overcome,” said Authority CEO Brian Kelly.
“The plan reflects our commitment to apply lessons learned and make organizational improvements necessary to deliver this project to initiate high-speed rail service between the Silicon Valley and the Central Valley as soon as possible, while completing environmental work and making important investments in Southern California,” Kelly said.
The draft business plan acknowledges cost increases affecting each segment of the project ranging from 20-35 percent and revised schedules that would push out delivery dates for the Silicon Valley to Central Valley Line and Phase 1 System. The draft plan acknowledges and responds to changed circumstances and emphasizes a new way of doing business moving forward.
In the face of these challenges, the draft business plan proposes to continue an investment strategy that builds infrastructure, linked over time, to provide mobility, economic and environmental benefits to Californians and initiate high-speed rail service as soon as possible.
Toward that end, the draft business plan identifies the following investment priorities:
* Meet Our Commitments to Federal Funding Partner: The Authority will complete the 119-mile segment in the Central Valley and complete environmental review for the entire Phase 1 System between San Francisco to Los Angeles/Anaheim by 2022, as required by the federal grant agreement.
* Extend the Valley-to-Valley Service from San Francisco to Bakersfield: The draft business plan recognizes the high ridership and revenue potential of linking the Silicon Valley with the Central Valley between San Francisco and Bakersfield.
* Deliver 224 Miles of High-Speed Rail Ready Infrastructure for Use by 2027: The draft business plan proposes to construct high-speed rail ready infrastructure in the Central Valley (Madera to Bakersfield) and in Silicon Valley (San Francisco to Gilroy) to reduce travel times for existing passenger rail systems, expand clean, electrified service, and prepare the corridors for testing and potential early high-speed rail operations.
* Continue Bookend Investment in Southern and Northern California: The draft business plan continues to prioritize improving Los Angeles Union Station, the Burbank to Anaheim corridor and the electrification of the Caltrain corridor in the Bay Area.
The draft business plan transparently identifies the project’s challenges, which include longer schedules and higher costs due in large part to inflation, increased contingencies and construction delays in the Central Valley.
Although high-speed rail continues to face many challenges—major progress has been made on many fronts, including:
* 20 active construction sites with thousands of Californians working along 119 miles in the Central Valley;
* Completion of three structures;
* Hundreds of businesses planning, designing and building the system — including small businesses, disadvantaged businesses and disabled veteran businesses — with more than 1,699 craft laborers dispatched to work on Central Valley construction projects.
The positive economic benefits from the program are tremendous, including $6 billion in total economic activity in California to date. Once operational, high-speed rail will breathe new life into local economies by encouraging the movements of residents and visitors between the major regions of the state like never before, while at the same time, protecting California’s environment.
“Building the nation’s first high-speed rail system, consistent with the will of the California voters, remains a tremendous challenge, but it is achievable if we remain committed to getting this transformative project done,” Kelly stated.
With the release of today’s draft business plan, the Authority is now seeking public comment as part of a 60-day public comment period that started today (March 9) and closes May 7, 2018.
The Authority is providing the following options for submitting comments:
* Online comment form through the Draft 2018 Business Plan website [here];
* By email at 2018businessplancomments@hsr.ca.gov;
* By U.S. mail to the Authority:
California High-Speed Rail Authority
Attn: Draft 2018 Business Plan
770 L Street, Suite 620 MS-1
Sacramento, CA 95814
* Voicemail comment at 916-384-9516;
* Provide public comment at a Board of Directors Meeting being held on March 20 (Sacramento) and April 17 (Los Angeles).
The Draft 2018 Business Plan, required by Assembly Bill 528 (Lowenthal, Chapter 237, Statutes of 2013), can be found online [here].
Like this:
Like Loading...
Related
REAL NAMES ONLY: All posters must use their real individual or business name. This applies equally to Twitter account holders who use a nickname.
2 Comments
What is the route through Santa Clarita/Canyon Country?
They’re still studying a set of alternative routes. It’s a process that’s required under the California Environmental Quality Act. You can take a look at the maps of the alternatives and the corresponding environmental documents here:
http://www.hsr.ca.gov/docs/programs/statewide_rail/proj_sections/palmdale_burbank/Palmdale_Burbank_New_Alternatives_Only.pdf
http://www.hsr.ca.gov/Programs/Statewide_Rail_Modernization/project_sections/index.html
I’m very excited for this project to get built.