[CH2M] – The Los Angeles County Metropolitan Transportation Authority has selected a team led by CH2M to provide the plans, specifications and estimates for the design of new high occupancy vehicle lanes along Interstate 5 in both directions between State Route 14 in Santa Clarita and Parker Road in Castaic.
As a component of the Measure R regional transportation improvement program, Metro will develop the I‐5 North Managed Lanes project with a goal of relieving congestion, increasing system efficiency and travel options, improving safety, maintaining the viability of the surrounding communities and meeting travel demand for future generations.
The PS&E scope of work for the 14-mile project includes:
* designing a HOV lane in each direction, as well as auxiliary lanes at various locations;
* extending the truck lane in the northbound direction from the Weldon Canyon overcrossing to Calgrove Boulevard;
* extending the truck lane in the southbound direction from Calgrove Boulevard to Pico Canyon Road/Lyons Avenue;
* extending two southbound truck lanes from Weldon Canyon to Calgrove Boulevard; and
* widening eight bridges.
When construction is completed, the managed lanes project will provide for improved mobility along this segment of I-5. Caltrans, the City of Santa Clarita and the County of Los Angeles are key partners in this project.
About CH2M
CH2M leads the professional services industry delivering sustainable solutions benefiting societal, environmental and economic outcomes with the development of infrastructure and industry. In this way, CH2Mers make a positive difference providing consulting, design, engineering and management services for clients in water; environment and nuclear; transportation; energy and industrial markets, from iconic infrastructure to global programs like the Olympic Games. Ranked among the World’s Most Ethical Companies and top firms in environmental consulting and program management, CH2M in 2016 became the first professional services firm honored with the World Environment Center Gold Medal Award for efforts advancing sustainable development. Connect with CH2M at www.ch2m.com; LinkedIn; Twitter; and Facebook.
Like this:
Like Loading...
Related
REAL NAMES ONLY: All posters must use their real individual or business name. This applies equally to Twitter account holders who use a nickname.
19 Comments
They just redid the rwy, should have done at rhat time. What a waste
It will cost hundreds of millions, take 5 to 7 years and cause more traffic.
Haven’t these people realized yet that HOV lanes are a 35 year experiment that hasn’t worked? Just give us all another lane to drive in!!!
Ive been saying the same thing for the last 35 years.
What doesn’t work about HOV lanes?
What doesn’t work?? Nobody is in them besides a small spattering of people. They sure don’t work like the idiots who run this state thought they would. Meanwhile, that’s another lane that my tax dollars is wasted on when I could be in that lane.
We will need it after all the new housing finishes.
The concrete is already there, just need yellow paint guys… What they they to do is stop bottlenecking the 14 fwy from Newhall pass to Placerita. They need to move the HOV lane over and squeeze in another lane.
It isn’t that difficult. They made the area worse. They need to hold people accountable for these terrible planing decisions
Wait a minute. Most of this stretch of highway was improved and had been under construction for the last three years already! And they couldnt finish it off with extra lanes then? What the heck?! This all should have been done when we were bottlenecked for those three years. The concrete is there, just paint the damn lines in and put up signs. There has been space sitting there since then. Ridiculously inefficient work.
What have they been doing for the last several years? The 5/14 interchange is a major clog after they finished.
No carpool lanes- more every car lanes…..they just dont work
The more difficult these people make it for those living in the suburbs to commute, the more likely it will be that residents will temporarily use mass transit and (out of disgust) ultimately relocate to the cities. The mega developers have lots of residential space to sell or rent downtown and their lobbyists have city, county, and state politicians in their pockets.
This was just done on the Newhall Pass and congestion is worse than ever. Why?!
Somebody screwed it up and nobody above them fixed it. This isn’t brain surgery, just fix it.
Why don’t they make it for everyone. We pay for it
I thought this was successfully fought down! It proves for MORE congestion to have HOV lanes – add a lane? GREAT! Make it for everyone, all the time.
Are they still going to do the FastTrack Fiasco? They call those the 1% lanes and have proven to be a failure all over the state.
Are they still ending the truck lane at Parker? that will be a traffic nightmare and the CATC fought that as well.
It’s also a Public/Private Partnership… that’s a problem, a big one.
I hope these are not the same people who designed the mess on northbound I-5 at the 14. That should be corrected before anyone starts designing more lines to the north.