Staff recommendation before the Board of Supervisors Tuesday, Oct. 20, 2015:

 

 

This action is to approve a change in work and the increased contract amount for a construction contract for State Route 126/Commerce Center Drive Interchange in the unincorporated community of Castaic.

 

IT IS RECOMMENDED THAT THE BOARD:

Find that the requested change in work related to construction of a cast-in-place, prestressed reinforced concrete bridge, asphalt concrete pavement, Portland cement concrete pavement on base material, reinforced concrete barriers, soil-cement bank stabilization, drainage facilities, traffic signals, intelligent transportation systems; with an increase in the construction contract amount of

$556,000; will have no significant effect on the environment and approve the change and increased contract amount for Project ID No. RDC0014507 – State Route 126/Commerce Center Drive Interchange; for revising pavement structural sections in the unincorporated community of Castaic, performed by C.A. Rasmussen, Inc.

 

 

PURPOSE/JUSTIFICATION OF RECOMMENDED ACTION

The purpose of the recommended action is to obtain approval from the Board for the change in this construction contract in support of the timely completion of the project while avoiding delays and the potential for claims.

 

The Honorable Board of Supervisors 10/20/2015

Page 2

 

Enclosed for the Board’s approval is a description of change in work, the necessary time extension, and the cost which is in excess of the Director of Public Works’ delegated limit required to complete the project.

 

Implementation of Strategic Plan Goals

The Countywide Strategic Plan directs the provisions of Operational Effectiveness/Fiscal Sustainability (Goal 1) and Integrated Services Delivery (Goal 3). Approval of this change will provide improved infrastructure to better serve the public and enhance the quality of life in the affected community.

 

FISCAL IMPACT/FINANCING

 

This change in work will have no impact to the County General Fund.

 

Project ID No. RDC0014507, with an increase in the construction contract amount of $556,000, is included in the Fifth Supervisorial District’s Transportation Improvement Program in the Road Fund Fiscal Year 2015-16 Budget.

 

If this change in work is not approved, contract completion will be delayed and increased costs incurred.

 

FACTS AND PROVISIONS/LEGAL REQUIREMENTS

 

The contract for the construction of this improvement was awarded on April 30, 2013, to a contractor with the lowest responsive bid in accordance with the State Public Contract Code and the Board’s directives.

 

ENVIRONMENTAL DOCUMENTATION

 

This change in work as described above and in the enclosure does not change any conditions which resulted in the original environmental findings.

 

CONTRACTING PROCESS

 

The contract provides that the contractor be compensated for the work resulting from a change to the original plans and specifications or changed conditions encountered during the course of construction. The cost is based on contract unit prices, time and materials, or negotiated under the provisions of the contract specifications.  The method for arriving at the cost of the change is included in the enclosure.

 

IMPACT ON CURRENT SERVICES (OR PROJECTS)

 

Approval of the requested change by the Board will ensure the timely completion of work under the contract and result in complete and usable facilities.

 

The Honorable Board of Supervisors 10/20/2015

Page 3

CONCLUSION

 

Please return one adopted copy of this letter to the Department of Public Works, Construction Division.

 

 

 

 

CHANGE IN WORK

October 20, 2015

 

 

PROJECT ID NO. RDC0014507 – State Route 126/Commerce Center Drive Interchange, (in the unincorporated community of Castaic), Supervisorial District 5 Contractor:  C.A. Rasmussen, Inc.

 

Project Description:

 

Construction of a cast-in-place, prestressed reinforced concrete bridge, asphalt  concrete pavement, Portland cement concrete pavement on base material, reinforced concrete barriers, soil-cement bank stabilization, drainage facilities, traffic signals, intelligent transportation systems, and the performance of other appurtenant work.

 

Change in Work:

 

Revise pavement structural sections                                                                    $556,000.00 Description of Change:

Due to the unavailability of suitable material at the mandatory borrow site, it is  necessary to revise the structural section for hot mix asphalt pavement for the roadway widening, shoulders, and ramps. A portion of the change in work was previously approved under delegated authority in the amount of $180,000 to stabilize the  subgrade. In order to complete the work, an additional 556,000 is  needed.  This exceeds the Director’s delegated authority limit and requires the Board’s approval.

 

The cost for this work is based on Section 3 of the contract specifications. No additional working days will be required because of this change.

Financial Information:

 

Sufficient funds for this project are included in the Fifth Supervisorial District’s Transportation Improvement Program in the Road Fund Fiscal Year 2015-16 Budget. The Road Fund will ultimately be reimbursed with Westside Bridge and Major Thoroughfare Construction Fee funds as fees are collected.

Comment On This Story
COMMENT POLICY: We welcome comments from individuals and businesses. All comments are moderated. Comments are subject to rejection if they are vulgar, combative, or in poor taste.
REAL NAMES ONLY: All posters must use their real individual or business name. This applies equally to Twitter account holders who use a nickname.

No Comments

    Leave a Comment


    LOS ANGELES COUNTY HEADLINES
    Tuesday, May 7, 2024
    The Los Angeles County Department of Parks and Recreation in cooperation with Friends of Castaic Lake will host Bark in the Park on Saturday, June 8 10 a.m.-2 p.m.
    Monday, May 6, 2024
    During Motorcycle Safety Awareness Month in May, the Los Angeles County Sheriff’s Department would like to remind drivers to always look twice for motorcycles.
    Friday, May 3, 2024
    Fire Service Day Open House will be held at all County of Los Angeles Fire Department fire stations on Saturday, May 4 from 10 a.m. to 5 p.m.
    Friday, May 3, 2024
    Explore Vasquez Rocks during the magical twilight and early evening full moon hours. These fun, collaborative, interpretive hikes are led by trained staff and volunteers and will highlight the park's natural and human history.
    Wednesday, May 1, 2024
    The Los Angeles County, Department of Public Social Services, and the Department of Public Health’s  CalFresh Healthy Living Program have launched the annual CalFresh Awareness Month campaign to remove barriers associated with applying for food assistance.

    Keep Up With Our Facebook
    Latest Additions to SCVNews.com
    1875 - John F. Powell, an Irish immigrant, becomes Justice of the Peace [story]
    John F. Powell
    The Los Angeles County Department of Parks and Recreation in cooperation with Friends of Castaic Lake will host Bark in the Park on Saturday, June 8 10 a.m.-2 p.m.
    June 8: Bark in the Park at Castaic Lake
    California State Assemblywoman Pilar Schiavo, D-Chatsworth, announced that 18 of her bills have successfully passed out of their respective Assembly policy committees, with most now moving to the Assembly Appropriations Committee.
    Schiavo Announces Key Progress on Legislation Package
    A 10-week Life Skills course underwritten by the Old West Masonic Lodge No. 813 in Newhall will be offered free to Santa Clarita Valley youth.
    Free Life Skills Classes for SCV Youth
    The Santa Clarita Valley Water Agency will hold a special board meeting on Monday, May 13 at 6 p.m. Board meetings have been temporarily relocated to the SCV Water Agency Training Room location at 23780 Pine St., Newhall, CA 91321.
    May 13: SCV Water Holds Special Board Meeting
    The 2024 California Institute of the Arts graduation ceremony will be held Friday, May 10 on the Valencia campus of CalArts. Honorary Degree recipients will include actor Keanu Reeves and director/writer/producer Gina Prince Bythewood.
    May 10: Keanu Reeves, Gina Prince Bythewood CalArts Graduation Honorees
    Graduation season is around the corner for the graduating seniors of the William S. Hart Union High School District.
    Hart High School District Graduation Schedule
    Members of the California Institute of the Arts community, industry representatives and friends and family journeyed to Los Angeles's Miracle Mile neighborhood to celebrate Character Animation students’ films at the 2024 Character Animation Producers’ Show.
    CalArts 2024 Character Animation Producers’ Show
    Princess Cruises, headquartered in Valencia, has announced it will return to San Juan, Puerto Rico after more than a decade, for a season of Southern Caribbean cruises onboard Grand Princess, from October 2025 through March 2026.
    Princess Cruises Announces Return to San Juan, Puerto Rico
    Join the Santa Clarita Valley Chamber of Commerce Wednesday, May 15, from 5:30 p.m. to 7:30 p.m., for the monthly After Hours Mixer, an evening of networking and fun at Chronic Tacos.
    May 15: SCV Chamber After Hours Mixer at Chronic Tacos
    Get ready to level up your small business game. The next Los Angeles Region Small Business Summit will be held Thursday, May 9 and features Supervisor Lindsey Horvath, Los Angeles County Team Department of Economic Opportuntiy, city of Los Angeles and partners at Mission College in Sylmar.
    May 9: Free Small Business Summit at Mission College
    College of the Canyons has captured the 3C2A Southern California Regional Championship, the ninth in program history, after turning its opening round lead into a four-stroke advantage over runner-up Cypress College on Monday, May 6 at Rio Bravo Country Club.
    COC Men’s Golf Wins SoCal Title, Advances to State Championship
    When every second counts, blood products can provide lifesaving care. The American Red Cross asks the public to give blood or platelets during Trauma Awareness Month in May to keep hospitals prepared for all transfusion needs, including emergencies.
    May is Trauma Awareness Month, Blood, Platelet Donors Needed
    The city of Santa Clarita has announced the pickleball courts at Bouquet Canyon Park will be closed on Wednesday, May 8, for necessary maintenance on the windscreens.
    May 8: Bouquet Canyon Park Pickleball Courts Closed for Maintenance
    The California Animal Welfare Association, the San Francisco Society for the Prevention of Cruelty to Animals and the American Society for the Prevention of Cruelty to Animals have announced the inaugural California Adopt-a-Pet Day will take place on Saturday, June 1.
    June 1: Inaugural California Adopt-a-Pet Day
    1861 - Andres Pico and partners granted state franchise to build toll road and cut 50-foot-deep cleft through (Newhall) Pass; they failed; Beale later succeeded [story]
    Andres Pico
    Gilbert, Arizona's Leah Burke has signed her National Letter of Intent to play soccer at The Master's University.
    Lady Mustangs Add Leah Burke to Soccer Roster
    CEDAR RAPIDS, Iowa  - The Master's University struggled against a high-energy Georgetown (KY) Tigers squad, losing in straight sets 23-25, 18-25, 20-25 in the championship match of the 2024 National Association of Intercollegiate Athletics Men's Volleyball Championships.
    Mustangs Drop NAIA Championship Game
    College of the Canyons student-athletes Nichole Muro (softball) and Owen Crockett (men's golf) have been named the COC Athletic Department's Women's and Men's Student-Athletes of the Week for the period running April 29 to May 4.
    COC Names Nichole Muro, Owen Crockett Athletes of the Week
    Step into the Heart of 1970s Texas at The MAIN as Front Row Center presents, "Lone Star, Laundry, and Bourbon."
    ‘Lone Star, Laundry, and Bourbon’ Coming to The MAIN
    Warmer weather, longer days and the sound of baseball is officially back!
    Ken Striplin | Santa Clarita Dodger Day Celebrates 45 Years
    Mental Health Hookup, in partnership with Henry Mayo Newhall Hospital, will conduct the third annual Stop the Stigma community event on May 18, from 10 a.m. to  2 p.m., on the Henry Mayo Newhall Hospital campus, located at 23803 McBean Parkway in Valencia.
    May 18: Stop the Stigma Community Event
    California State University, Northridge is set to open a first of its kind resource center in the CSU system to provide basic needs services such as food, clothing and wellness in a centralized location on campus.
    CSUN Set to Open First of Its Kind Student Resource Center
    The city of Santa Clarita’s Film Office released the list of three productions currently filming in the Santa Clarita Valley for the week of Monday, May 6 - Sunday, May 12.
    Three Productions Filming in Santa Clarita
    SCVNews.com